For the week of 4/1: Our crew is continuing with the clubhouse painting and expect to have it completed on Thursday. This will wrap up the scheduled painting in the community. Please contact our office with any questions. 

For the week of 3/25: We will have 2 crews on-site this week. One crew will be painting the clubhouse and expect to have it completed next week. Our iron crew will be on site Monday and Tuesday to paint backyard iron view fencing. Please remove all decor, vegetation, etc. from the view fencing to allow clear painting access and please secure all pets inside. Feel free to contact our office with any questions. 

For the week of 3/18: Our crew will be completing a few remaining sections of walls on Monday. This will wrap up the common area wall painting in the community. Feel free to contact our office with questions. 

For the week of 3/11: Our crew will be painting the common area walls in purple on the map below, starting near the canal on 28th St. Feel free to contact our office with any questions. 

For the week of 3/4: Our crew will be painting the common area walls marked in orange this week. Feel free to contact our office with any questions.