Overlook I

Hello Residents

For the week of 3/30/20: Prepping and painting for Buildings 7 & 8 will start on Monday and both are expected to be completed on Friday. Buildings 9 & 10 will be power washed on Thursday for prepping and painting the following week. Please remove/keep all decor off of the exterior of your home, secure pets indoors, and keep all patio furniture indoors or in the center of your patio (furniture will be covered for painting only. Please contact our office with any questions.

For the week of 3/23/20: Prepping and painting Buildings 5 & 6 will start on Monday and both are expected to be completed on Friday. Buildings 7 & 8 will be power washed on Thursday for prepping and painting the following week. Please remove/keep all decor off of the exterior of your home, secure pets indoors, and keep all patio furniture indoors or in the center of your patio (furniture will be covered for painting only. Please contact our office with any questions.

For the week of 3/16/2020: Painting for building 3 will continue throughout the week and building 4 will be started on Monday. Buildings 3 & 4 are both expected to be completed on Friday, weather permitting. Front entry doors will be painted on Thursday/Friday (there will be another day available if you cannot be home). Please remove/keep all decor off of the exterior of your home, secure pets indoors, and keep all patio furniture indoors or in the center of your patio (furniture will be covered for painting only. Please contact our office with any questions. 

For the week of 3/9/20: Buildings 1 & 2 will be completed on Monday (the buildings will be inspected on Tuesday for any needed touch ups). Painting for building 3 will continue on Tuesday but the completion date is TBD due to rainy weather predicted Tues-Fri. Please keep all decor off of the exterior of your home, secure pets indoors, and keep all patio furniture indoors or in the center of your patio (furniture will be covered for painting only. Please contact our office with any questions. 

For the week of 3/2/20: Buildings 1-3 (units 1001-1006) will be power washed, prepped, and painted throughout the week and are expected to be completed on Friday. Buildings 4-6 (units 1007-1012) will be power washed on Thursday for painting next week. Please remove all decor from the exterior of your home, secure pets indoors, and place all patio furniture indoors or in the center of your patio (furniture will be covered for painting only, not during power washing so it will get wet if left out). Please contact our office with any questions.