Kierland Heritage

Hello Residents

For the week of 3/30/20: Painting for Units 121-126 will be completed on Tuesday. Units 127-132 will be power washed and prepped, followed by painting throughout the week (& possibly into next week). Please remove/keep off all exterior decor, keep pets secured indoors, and place all patio furniture indoors or in the center of your patio (items will be covered during painting only). Feel free to contact our office with any questions.

For the week of 3/23/20: Painting for Units 113-120 will be completed on Monday. Units 121-126 will be power washed and prepped on Monday, followed by painting throughout the week. 121-126 are expected to be completed on Friday. Please remove/keep off all exterior decor, keep pets secured indoors, and place all patio furniture indoors or in the center of your patio (items will be covered during painting only). Feel free to contact our office with any questions.

For the week of 3/16/2020: Painting for Units 113-120 will continue throughout this week and into next week. Last weeks rain delayed the painting progress. Units 113-120 are expected to be completed Wed 3/25, weather permitting. Please remove/keep off all exterior decor, keep pets secured indoors, and place all patio furniture indoors or in the center of your patio (items will be covered during painting only). Feel free to contact our office with any questions.

  

For the week of 3/9/20: Painting for Units 113-120 will start on Monday. Due to the rainy weather predicted Tues-Fri, the date to complete 113-120 is TBD. Please remove/keep off all exterior decor, keep pets secured indoors, and place all patio furniture indoors or in the center of your patio (items will be covered during painting only). Feel free to contact our office with any questions.  

For the week of 3/2/20: Our crew will be finishing the exterior painting for Units 101-106 on Monday, with the exception of the iron. Our iron crew will be painting on Thursday. Units 107-112 will be prepped and painted this week and is expected to be completed on Friday. Units 113-120 will be power washed on Thursday & prepped on Friday. Please remove/keep off all exterior decor, keep pets secured indoors, and place all patio furniture indoors or in the center of your patio (items will not be covered during power washing, only during painting). Feel free to contact our office with any questions.  

For the week of 2/24/2020: We will be power washing, prepping, and painting Units 101-106 starting Monday and expect to have them completed on Friday. Units 107-112 will be power washed on Thursday. Please remove/keep off all exterior decor, keep pets secured indoors, and place all patio furniture indoors or in the center of your patio. Feel free to contact our office with any questions.  