Hello Residents

For the week of 3/30/20: Building 13 will be power washed and prepped starting Monday, followed by painting throughout the week. B13 is expected to be completed on Friday. Please remove/keep off all exterior decor, secure pets indoors, and place all patio furniture in the center of your patio or indoors (items will be covered during painting only). Feel free to contact our office with any questions. 

For the week of 3/23/20: Building 12 will be power washed and prepped starting Monday, followed by painting throughout the week. B12 is expected to be completed on Friday. Please remove/keep off all exterior decor, secure pets indoors, and place all patio furniture in the center of your patio or indoors (items will be covered during painting only). Feel free to contact our office with any questions. 

For the week of 3/16/2020: Building 11 will continue being prepped on Monday followed by painting and is expected to be completed on Thursday (last weeks rain delayed painting). Building 12 will be power washed on Friday. All of this is weather permitting. Please remove/keep off all exterior decor, secure pets indoors, and place all patio furniture in the center of your patio or indoors (items will be covered during painting only). Feel free to contact our office with any questions. 

For the week of 3/9/2020: Our crew will power wash and start prepping Building 11 on Monday. Painting is planned throughout the week with the building being completed on Friday. Due to the rainy weather predicted Tues-Fri, painting may be delayed and need to be continued next week. Please remove/keep off all exterior decor, secure pets indoors, and place all patio furniture in the center of your patio or indoors (items will be covered during painting only). Feel free to contact our office with any questions. 

https://www.paintingtitan.com/author/

ABOUT AUTHOR -