Hello Residents!

For the week of 5/2/22: The remaining common area walls (in green) will be painted this week and then culvert rails will be painted. Feel free to contact our office with any questions. 

For the week of 4/25/22: Common area walls in blue (upper section on first map) will be prepped throughout the week. Common area walls, along the route of the arrows on the second map, will be painted throughout the week. Please contact our office with any questions. 

For the week of 4/18/22: Common area walls will be prepped and painted this week (walls in RED were prepped last week [started Thursday]. Walls in GREEN will be prepped on Monday. Painting will start in the direction of the BLUE arrows). Feel free to contact our office with any questions. 