For the week of 4/6/20: The common area walls will continue being painting this week and will be completed on Friday. This will wrap up all wall painting in the community. Feel free to contact our office with any questions. 

For the week of 3/30/20: Our crew will restart prepping and priming common area walls in the community. Feel free to contact our office with any questions.

 

For the week of 2/17: Painting is on hold while colors are reviewed. 

For the week of 2/10: Stucco repairs on the common area walls will continue through Tuesday, with painting to follow (weather permitting). If you have any questions, please contact our office. 

For the week of 2/3: Our crew will begin scraping common area walls on Tuesday and will start stucco repairs on Wednesday (walls are marked in yellow). If you have any questions, please contact our office.