For the week of 10/24/22: We’ll make a final return to homes in parcel 8 (6333 & 6334 Viewmont) in an attempt to paint view fences that were previously skipped due to chicken wire, vegetation, locked gates, decor, pets in the yard, etc.. Please have your iron ready for painting and your yard accessible so your view fence can be completed.  Contact our office with any questions. 

For the week of 10/10/22: Wrought iron view fences marked in red in sections 8 and 9 will be painted this week. Please remove any vegetation, decor, chicken wire/critter fencing, etc from the iron so that we have clear access to paint the metal. Please allow yard access through your side gate and secure pets indoors. Please contact our office with any questions. 

For the week of 10/3/22: Wrought iron view fences marked in blue in section 8 will start being painted this week. Please remove any vegetation, decor, chicken wire/critter fencing, etc from the iron so that we have clear access to paint the metal. Please allow yard access through your side gate and secure pets indoors. Please contact our office with any questions. 

For the week of 9/26/22: Common walls in GREEN will continue being painted this week (rain caused delays last week, walls in yellow are completed). If you have any questions, please contact our office. 

For the week of 9/19/22: Common area walls in section 9 will continue to be painted. Please contact our office if you have any questions. 

For the week of 9/12/22: Common area walls in section 9 will finish being prepped and will start to be painted. If you have any questions, please contact our office. 

For the week of 9/5/22: We’re closed Monday for Labor Day. Common area walls in section 9 will be prepped and ramadas in section 5 will be painted this week. Please contact our office with any questions. 

For the week of 8/29/22: Common area walls in section 8 will be prepped on Monday and start being painted on Tuesday. Please contact our office with any questions. 

For the week of 8/22/22: Common area walls in section 7 (marked in green) will continue to be painted this week, followed by community gates. If you have any questions, please contact our office. 

For the week of 8/15/22: Common area walls in section 7 will prepped and painted this week. If you have any questions, please contact our office. 

For the week of 8/8/22: Common area walls in section 6 will be prepped and painted this week. Please contact our office with any questions. 

 

For the week of 8/1/22: Common area walls in section 5 will be prepped and painted this week. Please contact our office with any questions. 

For the week of 7/25/22: Common area walls in section 3 will be completed this week and common area walls in section 4 will be prepped and start being painted. Feel free to contact our office with any questions. 

For the week of 7/18/22: Common area walls in yellow (section 2) will be prepped and painted throughout the week and walls in section 3 will being being prepped and painted. If you have any questions, please contact our office.

For the week of 7/11/22: Common area walls marked in red will be prepped and painted throughout the week. If you have any questions, please contact our office. 

For the week of 7/4/22: We’ll be closed on Monday in observance of July 4th. Common area walls marked in green will be prepped and painted this week. Please contact our office with any questions. 