Vista Santa Fe

Hello Residents

For the week of 7/12/21:  We will be finished painting your beautiful community by this Wednesday!  Tuesday will be focused on painting all entry doors that were skipped throughout the process.  This includes units:  2, 3, 4, 13, 17, 21, 24, 48, 59, 62, 82, 83 and 84.  If you cannot be present on Tuesday, July 13 for painting, please contact our offices to schedule a time before Wednesday afternoon to have this done.  Feel free to contact our office with any questions.

For the week of 6/28/21:  Power wash and prep pool area on Monday.  We will be painting front doors at units 82-88.  Please make sure that all decor, lights, etc. are removed from all exterior parts of your home and that all patio furniture is in the middle of your patio (away from walls) or indoors.  Please secure any pets indoors.  Feel free to contact our office with any questions.

For the week of 6/21/21:  Unit 83 will be finished.  Garage doors will be painted for units 82-85.  We will begin masking on units 86-88. Please make sure that all decor, lights, etc. are removed from all exterior parts of your home and that all patio furniture is in the middle of your patio (away from walls) or indoors.  Please secure any pets indoors.  Feel free to contact our office with any questions.

For the week of 6/14/21:  Units 82-85 will begin power wash and prep Tuesday followed by prepping and painting the rest of the week and into next week.  Front doors for units 78-81 will be painted on Tuesday (someone needs to be home to open the door for front door painting).  Please make sure that all decor, lights, etc. are removed from all exterior parts of your home and that all patio furniture is in the middle of your patio (away from walls) or indoors.  Please secure any pets indoors.  Feel free to contact our office with any questions.

For the week of 6/7/21: Units 73-77 will be completed on Monday. Front and garage doors for units 73-77 will be painted on Tuesday (someone needs to be home to open the door for front door painting). Units 78-81 will be power washed on Tuesday, followed by prepping and painting the rest of the week and into next week. Please make sure that all decor, lights, etc. are removed from the exterior of your home and that all patio furniture is in the middle of your patio (away from the walls) or indoors. Please secure any pets indoors. Contact our office with any questions. 

For the week of 6/1/21: Units 73-77 will be power washed, primed, and painted Tuesday-Friday and into next week (closed Monday for Memorial Day). Front and garage doors for units 68-72 will be painted on Tuesday (someone needs to be home to open the door for front door painting). Please make sure that all decor, lights, etc. are removed from the exterior of your home and that all patio furniture is in the middle of your patio (away from the walls) or indoors. Please secure any pets indoors. Contact our office with any questions. 

For the week of 5/24/21: Front & garage doors for unit 63-37 will be painted on Monday (rescheduled from Friday due to wind). Units 68-72 will be prepped and painted throughout the week. Please make sure that all decor, lights, etc. are removed from the exterior of your home and that all patio furniture is in the middle of your patio (away from the walls) or indoors. Please secure any pets indoors. Contact our office with any questions. 

For the week of 5/17/21: Units 63-67 will be prepped and painted throughout the week & units 68-72 will be power washed on Friday. Please make sure that all decor, lights, etc. are removed from the exterior of your home and that all patio furniture is in the middle of your patio (away from the walls) or indoors. Please secure any pets indoors. Front doors for units 63-67 will be painted on Friday (someone needs to be home to open the door for painting). Feel free to contact our office with any questions.

For the week of 5/10/21: Units 58-62 will continue to be painted throughout the week. Front doors for these units will be painted on Friday (we do need someone home to open the door for painting). Units 63-67 will be power washed on Friday with prepping and painting happening next week. Please make sure that all decor, lights, etc. are removed from the exterior of your home and that all patio furniture is in the middle of your patio (away from the walls) or indoors. Please secure any pets indoors. Feel free to contact our office with any questions.

For the week of 5/3/21: Units 55-57 will be finished on Tuesday, except front doors. Front doors for units 53-57 will be painted on Wednesday (we do need someone home to open the door for painting). Units 58-62 will be power washed on Thursday followed by prepping and painting into next week. Please make sure that all decor, lights, etc. are removed from the exterior of your home and that all patio furniture is in the middle of your patio (away from the walls) or indoors. Please secure any pets indoors. Feel free to contact our office with any questions.

For the week of 4/26/21: Front doors for units 49-51 will be painted on Monday. Units 52-54 will be prepped Monday and painting will begin on Tuesday (weather permitting). Units 55-57 will be power washed on Thursday, followed by prepping and painting into next week. Please make sure that all decor, lights, etc. are removed from the exterior of your home and that all patio furniture is in the middle of your patio (away from the walls) or indoors. Please secure any pets indoors. Feel free to contact our office with any questions.

For the week of 4/19/21: Front doors for units 45-48 will be painted on Monday (someone must be home to open the door) and units 49-51 will be power washed followed by prepping and painting. Units 52-54 will be power washed on Wednesday followed by prepping and painting. 49-54 are expected to be completed next Tuesday. Please make sure that all decor, lights, etc. are removed from the exterior of your home and that all patio furniture is in the middle of your patio (away from the walls) or indoors. Please secure any pets indoors. Feel free to contact our office with any questions.

For the week of 4/12/21: Units 40-44 will continue being painted through Tuesday. Front doors for units 40-44 will also be painted on Tuesday (resident must be home in order for door to be painted). Units 45-48 will be power washed on Monday, followed by prepping and painting this week and into next week. Please make sure that all decor, lights, etc. are removed from the exterior of your home and that all patio furniture is in the middle of your patio (away from the walls) or indoors. Please secure any pets indoors. Feel free to contact our office with any questions.

For the week of 4/5/21: Units 36-39 will continue being painted through Tuesday. Units 40-44 will be power washed on Tuesday, followed by prepping and painting into next week. Front doors for units 30-39 will also be painted on Tuesday (resident must be home in order for door to be painted). Please make sure that all decor, lights, etc. are removed from the exterior of your home and that all patio furniture is in the middle of your patio (away from the walls) or indoors. Please secure any pets indoors. Feel free to contact our office with any questions.

For the week of 3/29/21: Units 35-39 will be power washed on Monday, followed by prepping and painting throughout the week. Please make sure that all decor, lights, etc. are removed from the exterior of your home and that all patio furniture is in the middle of your patio (away from the walls) or indoors. Please secure any pets indoors. Feel free to contact our office with any questions.

For the week of 3/22/21: Doors for units 25-29 will be painted on Monday and units 30-34 will be power washed and prepped. Painting for 30-34 will start on Tuesday and carry over into next week. Please make sure that all decor, lights, etc. are removed from the exterior of your home and that all patio furniture is in the middle of your patio (away from the walls) or indoors. Please secure any pets indoors. Feel free to contact our office with any questions.

For the week of 3/15/21: On Monday, units 20-24 will have their front and garage doors painted & units 25-29 will be power washed. Units 20-24 will be completed on Tuesday (there was no painting on Friday due to rain) and 25-29 will start being prepped. Please make sure that all decor, lights, etc. are removed from the exterior of your home and that all patio furniture is in the middle of your patio (away from the walls) or indoors. Please secure any pets indoors. Feel free to contact our office with any questions.

For the week of 3/8/21: Front doors for units 11-19 will be painted on Monday & 15-19 will be completed. Units 20-24 will be power washed on Monday, followed by prepping and painting. Please make sure that all decor, lights, etc. are removed from the exterior of your home and that all patio furniture is in the middle of your patio (away from the walls) or indoors. Please secure any pets indoors. Feel free to contact our office with any questions.

For the week of 3/1/21: Painting for units 11-14 will continue this week and be completed on Wednesday. Units 15-19 will be power washed on Tuesday, followed by prepping and painting into next week. Please make sure that all decor, lights, etc. are removed from the exterior of your home and that all patio furniture is in the middle of your patio (away from the walls) or indoors. Please secure any pets indoors. Feel free to contact our office with any questions.

For the week of 2/22/21: Units 7-10 will have the main body painted and units 6-10 will have the trim, garage doors, and front doors painted this week. Units 11-14 will be power washed on Wednesday. Please make sure that all decor, lights, etc. are removed from the exterior of your home and that all patio furniture is in the middle of your patio (away from the walls) or indoors. Please secure any pets indoors. Feel free to contact our office with any questions. 

For the week of 2/15/21: Units 1-5 will continue being painted through Tuesday. Units 6-10 will be power washed on Tuesday, followed by prepping and painting. Please make sure that all decor, lights, etc. are removed from the exterior of your home and that all patio furniture is in the middle of your patio (away from the walls) or indoors. Please secure any pets indoors. Feel free to contact our office with any questions. 

For the week of 2/8/21: Units 1-5 will be power washed on Monday followed by prepping and painting throughout the week and carrying over into next week. 1-5 are expected to be completed next Monday. Please make sure that all decor, lights, etc. are removed from the exterior of your home and that all patio furniture is in the middle of your patio (away from the walls) or indoors. Please secure any pets indoors. Feel free to contact our office with any questions. 

For the week of 2/1/21: Our crew will be removing the wood header above the front window and shutters for the units marked in yellow (units 1-44) on Monday and Tuesday (shutters will be replaced at a later date). Units 1-5 will begin being prepped on Tuesday and will be power washed on Friday. Stucco repairs for the units with the removed headers will start on Wednesday and carry on into next week. Please contact our office with any questions.