Hello Residents

For the week of 9/2: Our iron crew will be on-site on Friday only to continue painting the perimeter fencing and pillars.

For the week of 8/26: Our iron crew will be on-site Mon-Wed to paint the perimeter fencing only.

Village One painting is complete. 

For the week of 6/24: Painting for Building 18 will continue this week and is expected to be complete on Friday. We will have a second crew painting iron on Building 17 on Monday and Building 18 on Thursday. Please keep all decor off of the exterior of your building and keep any patio furniture in the center of your patio or indoors. Contact our office with any questions.

For the week of 6/17: Carports between buildings 16-18 will be painted on Monday. Please remove your vehicle by 6am to 3pm, we cannot be responsible for vehicles that are not removed. Building 18 will be power washed on Tuesday and prepped throughout the week (painting will begin Monday 6/24). Please remove all decor from the exterior of your building and keep any patio furniture in the center of your patio or indoors. We’ll have an iron crew on site on Thursday to paint the iron on Building 17. Contact our office with any questions.

For the week of 6/10: Our crew will continue painting Building 17 of 9210 E Mission Ln and expect to have it completed on Thursday or Friday. Please remove all decor off of the exterior of the building and keep any patio furniture in the center of your patio or indoors. Certain carports will be notified for power washing happening this Friday (notices will be posted on carport poles). Feel free to contact our office with any questions.

For the week of 6/3: Our crew will finish Building 16 of 9270 E Mission Ln on Tuesday. Building 17 of 9270 E Mission Ln will be power washed on Tuesday followed by prepping and painting into next week. Please remove all decor off of the exterior of the building and keep any patio furniture in the center of your patio or indoors. Feel free to contact our office with any questions.

For the week of 5/27: Building 16 of 9270 E Mission Ln will be prepped starting Tuesday and painted Thursday, weather permitting. We will be closed Monday in observance of Memorial Day. Please remove all decor off of the exterior of the building and keep any patio furniture in the center of your patio or indoors. Feel free to contact our office with any questions.

For the week of 5/20: Painting for Building 15 of 9275 E Mission Ln will be completed Wednesday or Thursday. Building 16 of 9275 E Mission Ln will be power washed on Thursday. Please remove all decor off of the exterior of the building and keep any patio furniture in the center of your patio or indoors. Feel free to contact our office with any questions. (Carports that were notified for Monday/Tuesday are now expected to be power washed Wednesday & painted Thursday, weather permitting).

For the week of 5/13: Painting for Building 14 of 9275 E Mission Ln will be completed on Monday and Building 15 of 9275 E Mission Ln will be power washed. Building 15 will be prepped on Tuesday/Wednesday and painting will begin on Thursday. Please remove all decor off of the exterior of the building and keep any patio furniture in the center of your patio or indoors. Feel free to contact our office with any questions.

For the week of 5/6: Painting for Building 14 of 9275 E Mission Ln will be started on Monday and is expected to be completed on Monday, May 13th. Please remove all decor off of the exterior of the building and keep any patio furniture in the center of your patio or indoors. We’ll have a second crew on site Monday-Wednesday to paint iron on balconies and stairways. Feel free to contact our office with any questions.

For the week of 4/29: Building 13 of 9275 E Mission Ln is being painted this week. Building 14 of 9275 E Mission Ln will be power washed on Wednesday and prepped on Friday for painting next week. All work is weather permitting. Please remove all decor off of the exterior of the building and keep any patio furniture in the center of your patio or indoors.  Feel free to contact our office with any questions.

 

For the week of 4/22: Our crew will continue painting Building 12 of 9345 N 92nd St. and expect to have it completed on Thursday. Our iron crew will be painting stairwells and balconies on buildings 10, 11, & 12. Building 13 of 9275 E Mission Ln. will be power washed on Wednesday and prepped on Thursday for painting next week. Please remove all decor off of the exterior of the building and keep any patio furniture in the center of your patio or indoors.  Feel free to contact our office with any questions. 

For the week of 4/15: Our crew will be painting carports marked in YELLOW on Monday. Carports in RED will be power washed on Tuesday and painted on Wednesday. We cannot be responsible for any vehicles not moved between 7am-3pm. (An email was sent out last week by Tri-City). Building 12 of 9345 N. 92nd St. will be power washed on Monday & prepped on Tuesday. Painting for building 12 will start on Thursday and expects to be completed next Wednesday 4/24. Please remove all decor off of the exterior of the building and keep any patio furniture in the center of your patio or indoors.  Feel free to contact our office with any questions. 

For the week of 4/8: Our crew will be painting Building 11 of 9345 N. 92nd St. and expect to have it completed on Monday 4/15. Please remove all decor off of the exterior of the building and keep any patio furniture in the center of your patio or indoors. We’ll also have our iron crew painting stairwells and balconies on Monday and Tuesday for buildings 8, 9, & 10. CARPORTS: Yellow will be washed on Friday & painted on Monday. We cannot be responsible for any vehicles not moved between 7am-3pm. (An email was also sent out from Tri-City). Feel free to contact our office with any questions.

For the week of 4/1: Our crew will be painting Building 10 of 9345 N. 92nd St. and expect to have it completed on Thursday. Building 11 of 9345 N. 92nd St. will be power washed on Thursday, followed by prepping and painting Friday and into the following week. Please remove all decor off of the exterior of the building and keep any patio furniture in the center of your patio or indoors. We’ll also have our iron crew painting stairwells and balconies for Buildings 8 and 9 on Thursday. Feel free to contact our office with any questions. 

For the week of 3/25: Our crew will continue painting Building 9 of 9340 N 92nd St (yellow) which was started last week, and expect to have it completed on Wednesday. Building 10 of 9345 N. 92nd St. will be power washed on Wednesday followed by prepping and painting. Please remove all decor off of the exterior of the building and keep any patio furniture in the center of your patio or indoors. Feel free to contact our office with any questions. 

For the week of 3/18: Our crew will continue painting Building 8 of 9340 N 92nd St (yellow) which was delayed due to the rain last week. Please remove all decor off of the exterior of the building and keep any patio furniture in the center of your patio or indoors. Feel free to contact our office with any questions. 

For the week of 3/11: Building 7 of 9340 N 92nd St (yellow) will be finished with painting on Monday. Building 8 of 9340 N 92nd St (yellow) was power washed on Friday and prepping begins on Monday, painting will follow. There is rain in the forecast which will prohibit our crew from painting, but they’ll return when the weather clears up. Our iron crew is expected to be painting the iron on the stairwells and balconies for buildings 6 & 7 on Wednesday (weather permitting). Please remove all decor off of the exterior of the building and keep any patio furniture in the center of your patio or indoors. Feel free to contact our office with any questions.

For the week of 3/4: Our crew will be prepping Building 7 of 9340 N 92nd St (yellow) on Monday and will start painting on Tuesday. B7 is expected to be completed Monday, 3/11. Please remove all decor off of the exterior of the building and keep any patio furniture in the center of your patio or indoors. Feel free to contact our office with any questions.

For the week of 2/25: Our crew will continue painting Building 6 (delayed due to rain) and expect to have it completed on Wednesday. Carports will be notified to advise of power washing (on Tuesday) and painting (Wednesday [marked in dark blue] & Thursday [marked in red]). Please remove your vehicle if parked in the notified carports between 7:00-3:00 on Wednesday and Thursday. Building 7 of 9340 N 92nd St will be power washed on Friday. Please remove all decor off of the exterior of the building and keep any patio furniture in the center of your patio or indoors. Feel free to contact our office with any questions.    

For the week of 2/18: No painting on Monday due to rain. On Tuesday, our crew will continue painting Building 6 of 9355 N 91st St (South) and expect to have it completed on Monday 2/25, weather permitting. Recent wet days have caused schedule delays. Please keep all decor off of the exterior of the building and keep any patio furniture in the center of your patio or indoors. Feel free to contact our office with any questions. 

For the week of 2/11: Our crew will finish painting Building 5 of 9355 N 91st St (South) on Monday which was delayed due to rain last week. Building 6 of 9355 N 91st St (South) will be power washed on Monday, prepped on Tuesday, and painting is expected to begin on Wednesday, weather permitting. Please remove all decor off of the exterior of the building and keep any patio furniture in the center of your patio or indoors. Feel free to contact our office with any questions. 

For the week of 1/28: Our crew will finish painting Building 4 of 9355 N 91st St (North) on Tuesday. Building 5 of 9355 N 91st St (South) will be power washed on Monday, prepped on Tuesday, and painting will start on Wednesday. Please remove all decor off of the exterior of the building and keep any patio furniture in the center of your patio or indoors. Feel free to contact our office with any questions.

For the week of 1/21: Our crew will finish painting Building 3 of 9355 N 91st St (North) on Tuesday due to rain delays last week. Building 4 of 9355 N 91st St (South) will be power washed on Tuesday and painting will start on Wednesday. Please remove all decor off of the exterior of the building and keep any patio furniture in the center of your patio or indoors. Feel free to contact our office with any questions. 

For the week of 1/14: Our crew will be painting Building 3 of 9355 N 91st St (North) and expect to have it completed 1/21. Please keep all decor off of the exterior of the building and keep any patio furniture in the center of your patio or indoors. Feel free to contact our office with any questions. 

For the week of 1/7/2019: Painting is continuing for Building 2 of 9355 N 91st St (North) and is expected to be completed on Thursday. Building 3 of 9355 N 91st St (North) will be power washed on Friday. Please remove all decor from the exterior of the building and keep any patio furniture in the center of your patio or indoors.

For the week of 12/31: Happy New Year! Our crew will be back on 1/2/2019 to repair drywall and prepping building 2 of 9355 N 91st St (North). Painting will start next Monday. Please remove all decor from the exterior of the building and keep any patio furniture in the center of your patio or indoors. 

For the week of 12/24: We will be closed from Monday 12/24 through Tuesday 1/1/2019 in celebration of Christmas and New Years. Our crew will return on January 2nd.

For the week of 12/17: Our crew will be painting the east side building of 9355 N 91st St (North) and expect to have it completed by Friday (time permitting). Please keep all decor off the exterior of the building and keep any patio furniture in the center of your patio or indoors. Feel free to contact our office with any questions. 

For the week of 12/10: Our crew will be power washing and painting the pool area starting Wednesday through Friday. The east side building of 9355 N 91st St (North) will be power washed on Friday for painting next week. Please remove all decor from the exterior of the building and place any patio furniture in the center of your patio or indoors. Please contact our office with any questions. 