Shadow Mountain Baseline

Hello Residents!

For the week of 3/4/24:  We are finishing up the last of the common areas this week.  Thank you for working with us to make your paint experience as easy as possible!  Feel free to contact our office with any questions.

For the week of 2/26/24:  We are finishing up the last building and will be painting carports and perimeter walls and fencing this week. Please remove and keep any exterior decor, lights, vegetation, etc. off the exterior of your unit and have any patio furniture in the center of your patio or indoors. Please secure pets inside. Feel free to contact our office with any questions.

For the week of 2/12/24: We will be painting the doors of Bldg. 28 this week.  We will also begin prepping Bldg. 29.  Please remove and keep any exterior decor, lights, vegetation, etc. off the exterior of your unit and have any patio furniture in the center of your patio or indoors. Please secure pets inside. Feel free to contact our office with any questions.

For the week of 1/29/24: Building 27 will be finishing painting doors and Bldg. 28 will begin prep on Monday.  Please remove and keep any exterior decor, lights, vegetation, etc. off the exterior of your unit and have any patio furniture in the center of your patio or indoors. Please secure pets inside. Feel free to contact our office with any questions.

For the week of 1/22/24: Building 26 will be finishing painting trim and Bldg. 27 will begin prep on Monday.  Please remove and keep any exterior decor, lights, vegetation, etc. off the exterior of your unit and have any patio furniture in the center of your patio or indoors. Please secure pets inside. Feel free to contact our office with any questions.

For the week of 1/15/24: Building 25 front doors will be painted and Bldg. 65 will begin  prep on Monday.  Please remove and keep any exterior decor, lights, vegetation, etc. off the exterior of your unit and have any patio furniture in the center of your patio or indoors. Please secure pets inside. Feel free to contact our office with any questions.

For the week of 1/8/24: Building 24 front doors will be painted and Bldg. 25 will begin power wash and prep on Monday.  Please remove and keep any exterior decor, lights, vegetation, etc. off the exterior of your unit and have any patio furniture in the center of your patio or indoors. Please secure pets inside. Feel free to contact our office with any questions.

For the week of 1/2/24: Happy New Year!  Building 24 will be washed and prepped and we will begin to paint this week.  Please remove and keep any exterior decor, lights, vegetation, etc. off the exterior of your unit and have any patio furniture in the center of your patio or indoors. Please secure pets inside. Feel free to contact our office with any questions.

For the week of 12/18/23: Buildings 21 and 22 will be finished painting trim and doors.  Building 23 has been washed and we will begin to prep and paint.  Please remove and keep any exterior decor, lights, vegetation, etc. off the exterior of your unit and have any patio furniture in the center of your patio or indoors. Please secure pets inside. Feel free to contact our office with any questions.

For the week of 12/11/23: Building 21 will have front doors painted Monday.  Building 22 will begin to be prepped and powerwashed on Monday as well.  Please remove and keep any exterior decor, lights, vegetation, etc. off the exterior of your unit and have any patio furniture in the center of your patio or indoors. Please secure pets inside. Feel free to contact our office with any questions

For the week of 12/4/23: Building 16 will still be painted and doors will be painted Monday.  Building 21 will begin to be prepped and powerwashed beginning Monday.  Please remove and keep any exterior decor, lights, vegetation, etc. off the exterior of your unit and have any patio furniture in the center of your patio or indoors. Please secure pets inside. Feel free to contact our office with any questions

For the week of 11/20/23: Building 14 will be completed on Monday (doors and trim). Building 15 will be power washed on Monday, followed by prepping and painting through Wednesday. We’ll be closed Thursday and Friday in observance of Thanksgiving. Please remove and keep any exterior decor, lights, vegetation, etc. off the exterior of your unit and have any patio furniture in the center of your patio or indoors. Please secure pets inside. Feel free to contact our office with any questions.

For the week of 11/13/23: Entry doors for Building 13 will be painted on Monday. Building 14 will be power washed on Tuesday, followed by prepping and painting. Please remove and keep any exterior decor, lights, vegetation, etc. off the exterior of your unit and have any patio furniture in the center of your patio or indoors. Please secure pets inside. Feel free to contact our office with any questions.

For the week of 11/6/23: Building 12 will be completed early this week (Mon/Tues). Entry doors for building 12 will be painted on Tuesday and building 13 will be power washed and prepped. Building 13 will be painted throughout the week. Please remove and keep any exterior decor, lights, vegetation, etc. off the exterior of your unit and have any patio furniture in the center of your patio or indoors. Please secure pets inside. Feel free to contact our office with any questions.

For the week of 10/30/23: Entry doors for Building 11 will be painted on Monday. Building 12 will be power washed on Monday followed by prepping and painting. Please remove and keep any exterior decor, lights, vegetation, etc. off the exterior of your unit and have any patio furniture in the center of your patio or indoors. Please secure pets inside. Feel free to contact our office with any questions.

For the week of 10/23/23: Building 20 will be completed this week. Building 11 will be power washed on Tuesday followed by prepping and painting. Please remove and keep any exterior decor, lights, vegetation, etc. off the exterior of your unit and have any patio furniture in the center of your patio or indoors. Please secure pets inside. Feel free to contact our office with any questions.

For the week of 10/16/23: Building 19 will be completed on Monday. Building 20 will be power washed and prepped starting Monday and painted throughout the week (& into next). Please remove and keep any exterior decor, lights, vegetation, etc. off the exterior of your unit and have any patio furniture in the center of your patio or indoors. Please secure pets inside. Feel free to contact our office with any questions.

For the week of 10/9/23: Building 18 will be finished early this week. Building 19 will be power washed, prepped, and painted starting on Monday. Please remove and keep any exterior decor, lights, vegetation, etc. off the exterior of your unit and have any patio furniture in the center of your patio or indoors. Please secure pets inside. Feel free to contact our office with any questions.

For the week of 10/2/23: Building 17 will be painted throughout the week. Building 18 will be power washed, prepped, and painting will starting Thursday and in to next week. Please remove and keep any exterior decor, lights, vegetation, etc. off the exterior of your unit and have any patio furniture in the center of your patio or indoors. Please secure pets inside. Feel free to contact our office with any questions.

For the week of 9/25/23: Building 10 will continue being painted this week. Building 17 will be power washed on Thursday. Please remove and keep any exterior decor, lights, vegetation, etc. off the exterior of your unit and have any patio furniture in the center of your patio or indoors. Please secure pets inside. Feel free to contact our office with any questions.

For the week of 9/18/23: Building 9 will be completed on Tuesday. Building 10 will be power washed on Wednesday followed by prepping and painting throughout the week and into next. Please remove and keep any exterior decor, lights, vegetation, etc. off the exterior of your unit and have any patio furniture in the center of your patio or indoors. Please secure pets inside. Feel free to contact our office with any questions.

For the week of 9/11/23: Building 8 will be completed on Monday. Building 9 will be power washed on Monday and then prepped and painted throughout the week. Please remove and keep any exterior decor, lights, vegetation, etc. off the exterior of your unit and have any patio furniture in the center of your patio or indoors. Please secure pets inside. Feel free to contact our office with any questions.

For the week of 9/4/23: We’re closed Monday for Labor Day. Building 8 will be prepped and painted throughout the week starting Tuesday. Please remove and keep any exterior decor, lights, vegetation, etc. off the exterior of your unit and have any patio furniture in the center of your patio or indoors. Please secure pets inside. Feel free to contact our office with any questions.

For the week of 8/28/23: Building 7 will be power washed on Monday followed by prepping and painting throughout the week. Building 8 will be power washed on Thursday, followed by prepping and painting into next week. Please remove and keep any exterior decor, lights, vegetation, etc. off the exterior of your unit and have any patio furniture in the center of your patio or indoors. Please secure pets inside. Front doors for buildings 6 & 7 will be painted on Friday. Feel free to contact our office with any questions.

For the week of 8/21/23: Building 6 will prepped and painted throughout the week. Please keep any exterior decor, lights, vegetation, etc. off the exterior of your unit and any patio furniture in the center of your patio or indoors. Please secure pets inside. Feel free to contact our office with any questions.

For the week of 8/14/23: Building 5 will be power washed on Monday followed by prepping and painting throughout the week. Building 6 will be power washed on Friday. Please remove any exterior decor, lights, vegetation, etc. and place any patio furniture in the center of your patio or indoors. Please secure pets inside. Feel free to contact our office with any questions.

For the week of 8/7/23: Building 4 will be power washed on Monday followed by prepping and painting throughout the week. Please remove any exterior decor, lights, vegetation, etc. and place any patio furniture in the center of your patio or indoors. Please secure pets inside. Feel free to contact our office with any questions. 

For the week of 7/31/23:  We are currently working on painting Building 2.  Building #3 will be pressure washed and prepped.  We will also be putting notices on doors Friday for door painting of Building 2 and anything we missed on Building 1.  Please remove any exterior decor, vegetation, etc. from your home and place any patio furniture in the center of your patio or indoors. Please allow access to your patio and secure pets inside. Feel free to contact our office with any questions. 

For the week of 7/24/23:  Building 1 (yellow) will be power washed and prepped.  Building 2 (red) will begin being prepped and power washed this Thursday.  Please remove any exterior decor, vegetation, etc. from your home and place any patio furniture in the center of your patio or indoors. Please allow access to your patio and secure pets inside. Feel free to contact our office with any questions. 