Hello Residents

For the week of 12/2: Building 8 will be power washed and prepped on Monday and is expected to be completed on Friday. Please remove all exterior decor and place any patio furniture in the center of your patio or indoors. Please contact our office with any questions.

For the week of 11/25: Due to the rain delays last week, painting for Building 7 is starting on Monday and is expected to be completed on Wednesday. Please keep all decor off the exterior of your home and keep any patio furniture in the center of your patio or indoors. Please contact our office with any questions. We’ll be closed Thursday and Friday in observance of Thanksgiving. 

For the week of 11/18: Building 7 is being power washed and prepped on Monday, followed by painting. B7 is expected to be completed on Friday (weather permitting). Please remove all exterior decor and place any patio furniture in the center of your patio or indoors. Please contact our office with any questions.

For the week of 11/11: Happy Veterans Day! Building 5 will be completed on Monday and Building 6 will be power washed, followed by prepping and painting throughout the week. Building 6 is expected to be completed on Friday. Building 7 will be power washed on Friday for painting next week. Please remove all exterior decor and place any patio furniture in the center of your patio or indoors. Please contact our office with any questions.

For the week of 11/4: Building 4 will be completed on Monday and Building 5 will be power washed. Prepping and painting will begin on Tuesday and B5 is expected to be completed on Monday 11/11. Building 6 will be power washed on Friday. Please remove/keep off all exterior decor and place any patio furniture in the center of your patio or indoors. Please contact our office with any questions. 

For the week of 10/28: Building 3 will be completed on Monday and Building 4 will be power washed and prepped. Building 4 will painted throughout the week and is expected to be complete on Friday (Building 5 is planned for power washing on Friday as well). Building 3 stairwells will be painted on Monday and on Building 4 stairwells will be painted on Friday. Please remove/keep off all exterior decor and place any patio furniture in the center of your patio or indoors. Please contact our office with any questions. 

For the week of 10/21: Building 2 is being completed on Monday (iron for stairs will be painted on Thursday & Friday). Building 3 will be power washed and prepped on Monday followed by painting throughout the week. 3 is expected to be completed on Friday and Building 4 is expected to be power washed. If you’re not home for your door edges to be painted, be advised that we will return on a future Saturday for your convenience (TBD). Please remove/keep off all exterior decor and place any patio furniture in the center of your patio or indoors. Please contact our office with any questions.

For the week of 10/14: Building 2 will be prepped on Monday and partially Tuesday, and painting will start Tuesday. Painting for building 2 is expected to be completed on Friday. Please remove/keep off all exterior decor and place any patio furniture in the center of your patio or indoors. Please contact our office with any questions. 

For the week of 10/7: Building 1 will be prepped and painted this week and is expected to be completed on Friday. Please remove/keep off all exterior decor and place any patio furniture in the center of your patio or indoors. Building 2 will be power washed on Thursday with prepping and painting to follow, carrying over into the following week. Please contact our office with any questions.

For the week of 9/30: Wood on Building 1 (1001/2001-1008/2008) will be primed on Monday only. Colors are under review at this time and our crew will return once they’re finalized. 