Olive Glen

Hello Residents!

For the week of 2/3: Our crew will be completing all painting on Monday. Please contact our office with any questions. 

For the week of 1/27/20: Building 6 will be finished on Tuesday. The clubhouse will be power washed and painted starting Monday. All work in the community is expected to be completed on Monday 2/3/2020. Please contact our office with any questions.

For the week of 1/20/20: Building 5 will be completed on Monday. Building 6 will be started on Tuesday and into next week. Please remove all exterior decor and place any patio furniture in the center of your patio or indoors. Please contact our office with any questions. 

For the week of 1/13/20: Building 5 will be painted this week and is expected to be finished next Monday 1/20. Building 6 will be power washed on Friday. Please keep off all exterior decor and keep any patio furniture in the center of your patio or indoors. Please contact our office with any questions.

For the week of 1/6/20: Building 4 will be painted throughout the week and is expected to be finished on Friday. Building 5 will be power washed on Friday. Please keep off all exterior decor and keep any patio furniture in the center of your patio or indoors. Please contact our office with any questions.

For the week of 12/30: Happy New Year! Our crew will be back on Thursday and Friday to complete Building 3 and power wash Building 4 (on Friday). Please remove all exterior decor and place any patio furniture in the center of your patio or indoors. Please contact our office with any questions.

For the week of 12/16: Painting for Building 2 will be finished on Monday and the prepping for Building 3 will begin. Painting for Building 3 will start on Wednesday. Our crew will complete as much as possible by Friday, but will complete B3 after our Christmas break. Our office and job sites will be closed from Dec 23 until Jan 2. Please contact our office before 12/23 with any questions. 

For the week of 12/9: Our crew will continue with Building 2 on Tuesday (no work on Monday due to rain) and expect to have it completed Tues 12/17. Building 3 will be power washed on Friday. Please remove/keep off all decor from the exterior of your building and place all patio furniture in the center of your patio or indoors. Feel free to contact our office with any questions. 

For the week of 12/2: Painting for Building 1 will start on Monday and is expected to be completed on Friday. Building 2 will be power washed on Thursday. Please remove/keep off all decor from the exterior of your building and place all patio furniture in the center of your patio or indoors. Feel free to contact our office with any questions. 

For the week of 11/25: Prepping for Building 1 is continuing this week with painting possibly beginning on Wednesday (or Monday 12/2). We will be closed Thursday & Friday in observance of Thanksgiving. Please keep all decor off of the exterior of your building and place all patio furniture in the center of your patio or indoors. Feel free to contact our office with any questions. 

For the week of 11/18: Our crew will be power washing and prepping Building 1 (see map) on Monday and Tuesday. Painting will follow. Date of completion is weather permitting. Please remove all decor from the exterior of your building and place all patio furniture in the center of your patio or indoors. Feel free to contact our office with any questions.