Hello Residents

For the week of 9/2: Our office is closed Monday for Labor Day. Common walls in Section 7 (75th Ave & Deer Valley) will be completed on Wednesday. Our iron crew will be painting culvert railings around the community on Wednesday and Thursday. This will wrap up all scheduled painting in the community. If you have any questions, please contact our office. 

For the week of 8/26: A small portion of Section 8 (71st Ave & La Senda Dr) will be completed and Section 7 (75th Ave & Deer Valley) will continue being prepped and painted this week. If you have any questions, please contact our office.

For the week of 8/19: Section 8 (71st Ave & La Senda Dr) common walls will continue and are expected to be completed on Wednesday. Section 7 (75th Ave & Deer Valley) are being prepped starting Monday and painting will follow. If you have any questions, please contact our office.

For the week of 8/12: The common walls in Section 6 (Hillcrest & Robin Ln) are being completed this week and the prepping for Section 8 (71st Ave & La Senda Dr) common walls will begin as well. If you have any questions, please contact our office.

For the week of 8/5: The common area walls for Section 5 (72nd Dr & north of Hillcrest) will be completed on Monday and the prepping of common walls in Section 6 (Hillcrest & Robin Ln) will begin on Monday as well. Section 6 will continue all week. Please contact our office with any questions. 

For the week of 7/29: Painting will continue for the common area walls for Section 5 (72nd Dr & north of Hillcrest) throughout the week. If you have any questions, please contact our office.

For the week of 7/22: Section 5 (72nd Dr & north of Hillcrest) common area walls will be prepped and painted throughout the week. If you have any questions, please contact our office.

For the week of 7/15: Our crew will continue prepping and painting walls in Section 4 (71st ave & north of Deer Valley Rd). Feel free to contact our office with any questions. 

For the week of 7/8: Painting for common walls in Section 4 will continue this week. Contact our office with any questions.

For the week of 7/1: Our crew will start prepping and painting common walls in Section 4 (71st ave & north of Deer Valley Rd). If you have any questions, please contact our office.

For the week of 6/24: Our will continue prepping and painting common area walls in Section 3. If you have any questions, please contact our office.

For the week of 6/17: Our crew will be prepping and painting the common area walls in Section 3 (71st ave & School Rd) this week. Feel free to contact our office with any questions.

For the week of 6/10: Our crew is continuing the repair and painting of common area walls in Section 2. Please contact our office with any questions. 

For the week of the 6/3: Our crew will continue painting the common area walls in Section 2 (69th Ave & south of Hillcrest) this week. Completion date is TBD for this section. 

For the week of 5/27: Our crew will be completing the painting of Section 1 (67th & Hillcrest) walls on Tuesday, as well as starting Section 2. They’ll be painting in Section 2 into next week.

For the week of 5/20: Our crew will be prepping and painting the common walls in Section 1 (67th Ave & north of Hillcrest) marked in GREEN on the map below. If you have any questions, please contact our office. 